The City of Sachse has already installed nearly 600 new
water meters throughout the City as a part of our project to modernize thetechnology of our domestic water system. The project is now moving into
the second phase, whereby the rest of the meters in the City will be replacedwith new water meters. The new water meters will provide more detailed
information regarding the water system and its usage after full conversion –allowing residents and City staff access to more complete information regarding
water use.
For Phase 2, Professional Meters, Incorporated (PMI) will becompleting the swap of approximately 7,000 water meters in the City, completing
the upgrade of the entire system. You may see PMI staff changing out yourwater meter over the next 3-4 months. PMI will be completing their work
neighborhood-by-neighborhood. During this time, access to water will onlybe interrupted for a few minutes at each home. If the City and/or PMI
find that more extensive work is required, they will coordinate with theindividual property owner. PMI will be scheduling meter change out times
with businesses on an individual basis, to ensure that water service is notinterrupted during high-use periods.
Thank you for your patience as we complete this important project
for our citizens!